475946 / MIK114185416 ARBOR HILLS LANDFILL, INC
10699 W 6 MILE RD, NORTHVILLE, MI 48168

Financial Assurance Data (13)

Financial Assurance Type
Account / Project Number
Current Balance
Bond Anniversary Date
Perpetual Care Fund 200166 $43,541,355.27
Account Number:
200166
Current Balance:
$43,541,355.27
PCF Type:
LCF BOND
Current Balance Date:
5/23/2023
Date Signed by Facility:
5/23/2023
PCF Has Been Released:
No
Date Executed by EGLE:
PCF Max:
$10,000,000.00 $10,000,000.00
Grantor:
ARBOR HILLS LANDFILL
Account Project Number:
200166
Current Balance:
$43,541,355.27
Instrument Type:
Current Balance Date:
5/23/2023
Anniversary Date:
Original Balance:
Bond Status:
Active
Effective Date:
Bond Status Date:
6/27/2023
Continuous Bond:
No
Grantor:
ARBOR HILLS LANDFILL
Disposal Area Types (0 records):

 

 
Perpetual Care Fund 0177505NS $0.00
Account Number:
0177505NS
Current Balance:
$0.00
PCF Type:
LCF STANDBY TRUST
Current Balance Date:
6/23/2023
Date Signed by Facility:
6/14/2023
PCF Has Been Released:
No
Date Executed by EGLE:
6/28/2023
PCF Max:
$10,000,000.00 $10,000,000.00
Grantor:
ARBOR HILLS LANDFILL
Account Project Number:
0177505NS
Current Balance:
$0.00
Instrument Type:
Current Balance Date:
6/23/2023
Anniversary Date:
Original Balance:
Bond Status:
Active
Effective Date:
Bond Status Date:
6/28/2023
Continuous Bond:
No
Grantor:
ARBOR HILLS LANDFILL
Disposal Area Types (0 records):

 

 
Financial Instrument - Surety Bond 852405 $1,040,000.00 6/11/2022
Account Number:
852405
Current Balance:
$1,040,000.00
PCF Type:
Current Balance Date:
9/13/2018
Date Signed by Facility:
PCF Has Been Released:
No
Date Executed by EGLE:
PCF Max:
$10,000,000.00 $10,000,000.00
Grantor:
Advanced Disposal Services Arbor Hills Landfill, Inc.
Account Project Number:
852405
Current Balance:
$1,040,000.00
Instrument Type:
SB - Surety Bond
Current Balance Date:
9/13/2018
Anniversary Date:
6/11/2022
Original Balance:
$1,577,000.00
Bond Status:
Active
Effective Date:
1/21/2010
Bond Status Date:
7/5/2023
Continuous Bond:
Yes
Grantor:
Advanced Disposal Services Arbor Hills Landfill, Inc.
Disposal Area Types (0 records):

 

 
New Row
Account Number:
Current Balance:
PCF Type:
Current Balance Date:
Date Signed by Facility:
PCF Has Been Released:
Date Executed by EGLE:
PCF Max:
$10,000,000.00 $10,000,000.00
Grantor:
Account Project Number:
Current Balance:
Instrument Type:
Current Balance Date:
Anniversary Date:
Original Balance:
Bond Status:
Active
Effective Date:
Bond Status Date:
5/18/2024
Continuous Bond:
Grantor:
Disposal Area Types (0 records):

 

 
$44,581,355.27 Total Open Financial Assurances:

Cost Estimate Data

Cost Estimate Type Amount Date
Closure / Post-Closure
$41,084,355.27
6/28/2023
Corrective Action
$2,457,000.00
6/28/2023
Other
$1,040,000.00
6/28/2023
Total Cost Estimate Data
$44,581,355.27
Save

Financial Assurance Action (13)

Due Date
Completion Date
Action
6/29/2024 CE - Cost Estimate
Due Date:
6/29/2024
Action:
Cost Estimate
Responsible Person:
Guilmette, Katriena
Branch:
SWTU - Solid Waste - Technical Unit
Completion Date:
Comments:
9/26/2022 6/28/2023 CE - Cost Estimate
Due Date:
9/26/2022
Action:
Cost Estimate
Responsible Person:
Guilmette, Katriena
Branch:
SWTU - Solid Waste - Technical Unit
Completion Date:
6/28/2023
Comments:
Completed with OL App.
9/26/2021 8/12/2022 CE - Cost Estimate
Due Date:
9/26/2021
Action:
Cost Estimate
Responsible Person:
Guilmette, Katriena
Branch:
SWTU - Solid Waste - Technical Unit
Completion Date:
8/12/2022
Comments:
9/26/2019 CE - Cost Estimate
Due Date:
9/26/2019
Action:
Cost Estimate
Responsible Person:
Guilmette, Katriena
Branch:
SWTU - Solid Waste - Technical Unit
Completion Date:
Comments:
3/13/2018 9/20/2018 CE - Cost Estimate
Due Date:
3/13/2018
Action:
Cost Estimate
Responsible Person:
Ring, Margie
Branch:
SWTU - Solid Waste - Technical Unit
Completion Date:
9/20/2018
Comments:
3/13/2016 11/30/2016 CE - Cost Estimate
Due Date:
3/13/2016
Action:
Cost Estimate
Responsible Person:
Ring, Margie
Branch:
SWTU - Solid Waste - Technical Unit
Completion Date:
11/30/2016
Comments:
Covers 3/13/2017 update
3/13/2015 2/13/2015 CE - Cost Estimate
Due Date:
3/13/2015
Action:
Cost Estimate
Responsible Person:
Ring, Margie
Branch:
SWTU - Solid Waste - Technical Unit
Completion Date:
2/13/2015
Comments:
6/9/2013 3/11/2014 CE - Cost Estimate
Due Date:
6/9/2013
Action:
Cost Estimate
Responsible Person:
Ring, Margie
Branch:
SWTU - Solid Waste - Technical Unit
Completion Date:
3/11/2014
Comments:
Updated with new license.
6/9/2012 10/3/2012 CE - Cost Estimate
Due Date:
6/9/2012
Action:
Cost Estimate
Responsible Person:
Ring, Margie
Branch:
SWTU - Solid Waste - Technical Unit
Completion Date:
10/3/2012
Comments:
6/9/2011 10/19/2011 CE - Cost Estimate
Due Date:
6/9/2011
Action:
Cost Estimate
Responsible Person:
Ring, Margie
Branch:
SWTU - Solid Waste - Technical Unit
Completion Date:
10/19/2011
Comments:
New Row
Due Date:
Action:
Responsible Person:
Branch:
Completion Date:
Comments: