399054 / MID980608657 RIVERVIEW LAND PRESERVE
20863 GRANGE ROAD, RIVERVIEW, MI 48193

Financial Assurance Data (6)

Financial Assurance Type
Account / Project Number
Current Balance
Bond Anniversary Date
Perpetual Care Fund 20-75-067-7835175 $0.00
Account Number:
20-75-067-7835175
Current Balance:
$0.00
PCF Type:
LCF STANDBY TRUST
Current Balance Date:
7/28/2023
Date Signed by Facility:
7/27/2023
PCF Has Been Released:
No
Date Executed by EGLE:
7/27/2023
PCF Max:
$10,000,000.00 $10,000,000.00
Grantor:
CITY OF RIVERVIEW
Account Project Number:
20-75-067-7835175
Current Balance:
$0.00
Instrument Type:
Current Balance Date:
7/28/2023
Anniversary Date:
Original Balance:
Bond Status:
Active
Effective Date:
Bond Status Date:
8/1/2023
Continuous Bond:
No
Grantor:
CITY OF RIVERVIEW
Disposal Area Types (0 records):

 

 
Perpetual Care Fund 18137492-00-000 $32,555,000.00
Account Number:
18137492-00-000
Current Balance:
$32,555,000.00
PCF Type:
LCF LETTER OF CREDIT
Current Balance Date:
7/28/2023
Date Signed by Facility:
7/28/2023
PCF Has Been Released:
No
Date Executed by EGLE:
PCF Max:
$10,000,000.00 $10,000,000.00
Grantor:
CITY OF RIVERVIEW
Account Project Number:
18137492-00-000
Current Balance:
$32,555,000.00
Instrument Type:
Current Balance Date:
7/28/2023
Anniversary Date:
Original Balance:
Bond Status:
Active
Effective Date:
Bond Status Date:
8/1/2023
Continuous Bond:
No
Grantor:
CITY OF RIVERVIEW
Disposal Area Types (0 records):

 

 
New Row
Account Number:
Current Balance:
PCF Type:
Current Balance Date:
Date Signed by Facility:
PCF Has Been Released:
Date Executed by EGLE:
PCF Max:
$10,000,000.00 $10,000,000.00
Grantor:
Account Project Number:
Current Balance:
Instrument Type:
Current Balance Date:
Anniversary Date:
Original Balance:
Bond Status:
Active
Effective Date:
Bond Status Date:
5/17/2024
Continuous Bond:
Grantor:
Disposal Area Types (0 records):

 

 
$32,555,000.00 Total Open Financial Assurances:

Cost Estimate Data

Cost Estimate Type Amount Date
Closure / Post-Closure
$32,554,894.66
7/28/2023
Corrective Action
$0.00
Other
$0.00
Total Cost Estimate Data
$32,554,894.66
Save

Financial Assurance Action (15)

Due Date
Completion Date
Action
5/7/2024 CE - Cost Estimate
Due Date:
5/7/2024
Action:
Cost Estimate
Responsible Person:
Guilmette, Katriena
Branch:
SWTU - Solid Waste - Technical Unit
Completion Date:
Comments:
5/7/2023 7/28/2023 CE - Cost Estimate
Due Date:
5/7/2023
Action:
Cost Estimate
Responsible Person:
Guilmette, Katriena
Branch:
SWTU - Solid Waste - Technical Unit
Completion Date:
7/28/2023
Comments:
Took 5 months of back and forth with Riverview and their Bank to get
financial assurance transferred over to the LCF
5/7/2022 CE - Cost Estimate
Due Date:
5/7/2022
Action:
Cost Estimate
Responsible Person:
Guilmette, Katriena
Branch:
SWTU - Solid Waste - Technical Unit
Completion Date:
Comments:
5/7/2021 6/4/2021 CE - Cost Estimate
Due Date:
5/7/2021
Action:
Cost Estimate
Responsible Person:
Guilmette, Katriena
Branch:
SWTU - Solid Waste - Technical Unit
Completion Date:
6/4/2021
Comments:
1/15/2020 4/8/2020 CE - Cost Estimate
Due Date:
1/15/2020
Action:
Cost Estimate
Responsible Person:
Guilmette, Katriena
Branch:
SWTU - Solid Waste - Technical Unit
Completion Date:
4/8/2020
Comments:
Completed with license application.
1/15/2019 6/5/2019 CE - Cost Estimate
Due Date:
1/15/2019
Action:
Cost Estimate
Responsible Person:
Ring, Margie
Branch:
SWTU - Solid Waste - Technical Unit
Completion Date:
6/5/2019
Comments:
1/15/2018 5/8/2018 CE - Cost Estimate
Due Date:
1/15/2018
Action:
Cost Estimate
Responsible Person:
Ring, Margie
Branch:
SWTU - Solid Waste - Technical Unit
Completion Date:
5/8/2018
Comments:
3/30/2015 12/1/2015 CE - Cost Estimate
Due Date:
3/30/2015
Action:
Cost Estimate
Responsible Person:
Ring, Margie
Branch:
SWTU - Solid Waste - Technical Unit
Completion Date:
12/1/2015
Comments:
3/30/2014 4/15/2014 CE - Cost Estimate
Due Date:
3/30/2014
Action:
Cost Estimate
Responsible Person:
Ring, Margie
Branch:
SWTU - Solid Waste - Technical Unit
Completion Date:
4/15/2014
Comments:
3/30/2013 5/21/2013 CE - Cost Estimate
Due Date:
3/30/2013
Action:
Cost Estimate
Responsible Person:
Ring, Margie
Branch:
SWTU - Solid Waste - Technical Unit
Completion Date:
5/21/2013
Comments:
New Row
Due Date:
Action:
Responsible Person:
Branch:
Completion Date:
Comments: