Permit to Install (PTI) Applications for
Coal-Fired Power Plants

The following PTI was issued on May 12, 2008.  The permit decision was appealed to the USEPA Environmental Appeals Board (EAB).  The applicant sent a request to void this permit on May 7, 2009 (received May 11, 2009).  The Air Quality Division voided the permit to install on May 12, 2009.  For more information visit the NSR Public Notice Documents page (View).

___________________________________

Northern Michigan University – Ripley Heating Plant, Marquette, 49855

State Registration No. M3792
PTI Application No. 60-07
Permit Engineer:  David Riddle, (517) 373-7081, RiddleD@michigan.gov

The permit was issued on May 12, 2008.  The permit decision has been appealed to the USEPA Environmental Appeals Board (EAB).  Currently, the Office of the Attorney General staff is working on this matter.

Section

Item Description

Date Received

 

1.0 -7.0, Appendix A - G

PTI Application Package

2/5/2007

View

Addendum

Addendum to PTI Application Package 9/21/2007

View

Letter Campus-wide HAPs Emissions and Rule 112(g) Concerns 4/24/2008 View
Letter Permit Voided - Agency Action 5/12/2009 View

 ___________________________________